Salesforce

What is the difference between the Task Due Date and the Step Due Date columns and how to set them?

« Go Back

Information

 
TitleWhat is the difference between the Task Due Date and the Step Due Date columns and how to set them?
URL Name000019493
SummaryTo set a date in these columns you do this from the Change Task and Step Due Dates window.
Scope/EnvironmentWorldServer
Question
What is the difference between the Task Due Date and the Step Due Date columns and how to set them?

User-added image
 
Answer
In the Modern User Interface, in the Project's tasks page, to access this window you:
  1. Select a task
  2. Go to the Task Options button
  3. Select Change Due Dates
User-added image

The Task Due Date and Step Due Date columns are controlled as highlighted below.

User-added image