Flow - How to set a delivery date for an individual task
000015139|3/2/2021 12:05 PM
Scope/Environment
Flow
Question
You'd like to ensure that a translation task is completed before a project's delivery date so that there is sufficient time to proofread the translations, for example.
Answer
1. Select the appropriate task from the workflow. 2. Click Update under Workflow Operations. 3. Set a delivery date for this task in the Delivery field. 4. Click Update to apply the changes to the task.